Delegated contracting authority: compensation for additional works

In the construction of an emergency services centre, company B., awarded two lots, received the final statements of account notified on 2 April 2013 after acceptance with reservations. The company asked the administrative court for compensation for additional works. The Nancy Administrative Court of Appeal recalls that, even where conditions are irregular, the holder of a lump-sum contract is entitled to compensation for additional works if they were useful to the contracting authority or indispensable to proper performance. Company B. disputed the allocation of the detailed design studies, but the court confirmed that this allocation complied with the legal provisions. B. did not prove that its studies were indispensable or outside its contractual obligations. (CAA Nancy, 14 May 2024, req. no. 20NC00519).

On the same topic

April-26

Governance before kilometres: regulating a railway revival

This article features insights from Elvira Palomino Alarcón, CEO and Director of Legal Engineering at TrAInsolutions, on railway governance and project structuring. In “Governance...

622915235_1267620985464775_1651935026790744302_n

Megaprojects don’t collapse overnight — they drift into claims: legal engineering as an X-ray of governance and dispute prevention

In the InHouse Practice section, Elvira Palomino Alarcón approaches Legal Engineering as a true “strategic X-ray” of megaprojects. Through a hybrid approach combining law...

Modern office lobby with a wall relief depicting infrastructure, energy and rail, and professionals in discussion, one of them wearing a hard hat

Megaprojects: Claim Management and digital transformation — what challenges for organisations?

In contract-intensive sectors – infrastructure, rail, energy, construction, industry or large IT programmes – Claim Management has become a strategic issue. On megaprojects, cost,...